Capital Project
High School
The High School project consists of renovations and infrastructure improvements to the High School Building as follows:
- Tech/STEM Space Renovations: Full demolition of existing footprint and installation of new finishes, existing equipment, new equipment and all associated MEPFP infrastructure.
- Building Control Upgrades: Full replacement and update to the Building Management System for MEPFP Controls.
Site improvements include installation of new concrete pad, fencing and infrastructure for a new Dust Collector to service the new Tech Space and some minor hardscapes work for a new Overhead Door entry point to the space.
Middle School
The Middle School project consists of major renovations, site work and infrastructure improvements to the Middle School Building as follows:
- Site Improvements:
- Reconstruction of existing tennis courts for the conversion to a synthetic turf playing surface.
- Construction of a new play equipment area including new infrastructure and equipment for community and District use.
- Stormwater improvements/replacement of storm piping.
- Emergency Service Updates: Renovations to include new EM lighting throughout, new gas shutoff valve replacements and additions and miscellaneous emergency power generation hookups.
- Building Control Upgrades: Full replacement and update to the Building Management System for MEPFP Controls.
- Boiler System Replacement: Full replacement of existing Boiler System and install of new system to include all equipment, Domestic Water systems, Controls, Pumps, etc.
- Roof Replacement: Selective Roof replacements and repairs in various areas to achieve new 30-year and 20-year warranties.
- Main Office A/C and Ceiling Replacement: Renovation of ceilings and lighting to accommodate full replacement of existing mechanical equipment and new equipment install to add air conditioning service to the Space. Scope includes some exterior sitework for new concrete pads, landscaping, etc. to accommodate new ground-mounted Condensing Units.
Elementary School
The Harold O. Brumsted Elementary School project consists of infrastructure improvements to the Elementary School Building as follows:
- Building Control Upgrades: Full replacement and update to the Building Management System for MEPFP Controls.





High School: Wood Floor & CMU Wall Demo

High School: Floor Infill

High School: Steel Structure/Welding

High School: Miscellaneous Demolition

High School & Elementary School: Control Valves

Work on the Athletic Field
April 2026

HS: PP-C Panel Replacement

MS: Sanitary Line Replacement

HS: Exhaust Fan

MS: MH-1

HS: Pipes Rough In

HS & ES: Control Valves

HS: Tech Room Above Ceiling Rough In

MS: Storm Pipe Lining

MS: Playground Installation
May 2026

MS: Playground Complete

MS: Turf Complete

MS: Pool Filter/Valve Replacement

MS: Boiler Room Abatement

HS: Dust Collector Ductwork

HS, MS, & ES: Control Updates

HS: Site Work

HS: New Curbs

MS: New Pool Roof
June 2026

MS: Incinerator Abatement

MS: Basketball Court New Asphalt

MS: Roof Work

MS: Boiler Room Demo

HS: Lawn Restoration

HS: Drywall Tech Room

HS: Panel Wiring

HS: Dust Collector, RTU, MAU

HS: RTU Control Upgrade
July 2026

MS: Main Office ACCU

MS: Corridor Lights

MS: Scoreboard

MS: Boiler Room

MS: New Building Boilers

HS: Wood Shop Flooring Prep

HS:Â Computer Lab Floor

HS: Wood Shop Paint and Floor

HS: Corridor Rebranding